IODP Expedition 321T: Juan de Fuca Cementing Operations
Site U1301 Summary
PDF file is available for download.
3 July 2009
IODP
Expedition 301 was part of a series of expeditions and experiments to quantify
hydrogeologic, lithologic, biogeochemical, and microbiological properties,
processes, and linkages on the eastern flank of the Juan de Fuca Ridge. Borehole observatories installed during IODP Expedition 301
were designed to seal open holes so that thermal, pressure, chemical conditions
could equilibrate following the dissipation of the drilling disturbance; to
facilitate collection of fluid and microbiological samples and temperature and
pressure data and to serve as long-term monitoring points for large-scale crustal
testing (Fisher et al., 2005b). Unfortunately, the CORKs installed in Holes
U1301A and U1301B were not sealed as intended (Fisher et al., 2005a), and data
and samples collected during subsequent ROV and submersible servicing
operations have shown that both observatory systems are leaking. The main
objective of IODP Expedition 321T is to pump cement into re-entry cones around
subseafloor borehole observatories in Holes U1301A and U1301B, in order to seal
the systems and permit later completion of long-term hydrogeologic monitoring,
sampling, and experiments. Expedition 321T was not intended to collect any data
or samples. Only observatory sealing operations were conducted.
Cementing Operations
Cementing
operations began with Hole U1301B as re-entry at this hole was somewhat less
challenging through the open slot on the platform compared to re-entry through
a screened 12"diameter opening at Hole U1301A.
Hole U1301B (47° 45.229' N, 127° 45.826' W; Seafloor depth 2667.8 m DRF)
After
lowering thrusters and stabilizing the ship over the location coordinates, the
cementing Bottom Hole Assembly (BHA) was picked up. This consisted of the
cementing stinger (made from a joint of 5-1/2" drill pipe cut in half at a 60°
angle and with four staggered 3" diameter holes drilled in the lower 9", 1
joint of 5-1/2" transition drill pipe, X/O, two 8-1/4" diameter control length
drill collars (CLDC), tapered drill collar (TDC), and another joint of 5-1/2"
transition drill pipe. The drill string was run to a depth of 1376.2 m below
rig floor (DRF) and the VIT/subsea TV was deployed. The drill string trip was
then completed to a depth of 2664.3 m DRF (4.4 m above reentry cone rim) and
spaced out for reentry. A drill string wiper "pig" was pumped down to clean any
remnant mud from the pipe. Pump strokes were monitored and timed as a
crosscheck on the calculated displacement of the drill string. The exit of the
"pig" was marked by a large cloud of mud that billowed out of the end of the
drill pipe upon its arrival. The lo-torque valve and cementing system integrity
was then pressure tested and at 1030 hr 30 June 2009 vessel maneuvering for the
first reentry attempt began. The reentry target was a single (1 of 12) pie
shaped window in the Hole U1301B CORK platform. The platform was reentered at
1215 hr that same day after 2 hours and 15 minutes of maneuvering. The
driller's task was made more complicated by the fact that the top of the cone
rim was 1.1 m below seafloor depth (DSF), which meant drill string activity
around the cone/platform vicinity stirred up the mud and obscured visibility
for several minutes.
At 1245 hr, after observing the drill string and seafloor installation for stability
and heave- out potential, the decision was made to move forward with the
cementing operation. Preparations began for mixing the first batch of cement.
At 1300 hr the actual cementing mixing operation was initiated and by 1350 hr a
total of 60 barrels (bbls) of 15.8 pound per gallon (ppg) class G neat cement
blended with Cello-flake lost circulation material (LCM) was mixed up with
fresh water and displaced into the pipe. This was chased with 20 barrels of
fresh water using the Halliburton cementing pump followed by 120 barrels of sea
water displaced with the Triplex rig pumps. The drill string was pulled clear
of the top of the reentry cone (TOC) at 1420 hr 30 June with ~10 barrels of
cement still falling from the drill string. This was done to avoid the
potential of pumping water into the reentry cone and diluting the cement
slurry.
Hole U1301A
(47° 45.210' N, 127° 45.833' W; Sea floor depth: 2667.3 m DRF)
The
cementing unit was cleaned and the tanks flushed while offsetting the ship the
35 m to Hole U1301A. The drill pipe was also flushed and a drill string pig was
pumped to wipe away any remnant cement. Maneuvering for reentry at Hole U1301A
began at 1530 hr. This time the reentry target was more challenging: one of
eight 12 inch diameter holes in the old style "solid" CORK platform. Reentering
through one of these holes required using the cement stinger to push through
the steel grating that had been tack-welded in place below the platform on
Expedition 301, requiring careful timing and control of weight on bit. The Hole
U1301A platform was reentered at 1815 hr after only 2-3/4 hr of maneuvering
time. The cone rim at this site was 1.4 m DSF and covered with a layer of fine
sediment. Whenever the bit would drag on the platform surface it would stirred
up a cloud of sediment obscuring visibility for several minutes.
For
this hole, a total of 114 bbls of 15.8 ppg "blended" cement was mixed up and
displaced in the same manner as in Hole U1301B. Mixing ended at 2000 hr, the
batch was chased with 20 bbls of fresh water using the Halliburton cementing
pump followed by an additional 120 bbls of sea water using the rig pumps. The
pipe was pulled clear of the TOC at 2020 hr 30 June with another ~10 barrels of
cement still falling from the drill string.
Return to Hole U1301B and Hole U1301B
Hole
U1301B platform was reentered for the second time at 2250 hr requiring only 65
minutes. Preparations for mixing the second batch of cement for the hole
started immediately. 70 bbls of
15.8 ppg "blended" cement was displaced into pipe, chased with 20 bbls of fresh
water using Halliburton cementing pump, and an additional 120 bbls of sea water
using the rig pumps. The pipe was pulled clear of the TOC at 2355 hr 30 June
again with ~10 barrels of cement still falling from the drill string. After the
second cement job, visual observations at Hole U1301B indicated that the
reentry cone appeared to be full of cement as well as the surrounding area
outside of cone. The cementing unit was
cleaned and the tanks flushed while offsetting the ship 35 m back again to Hole
U1301A. Visual observations at Hole U1301A indicated that the reentry cone was
full of cement as well as the surrounding area outside of cone. The cementing
equipment was rigged down, the subsea TV/VIT was recovered back aboard, and the
drill pipe was tripped back to the surface ending cementing operations at Site
U1301 at 0900 hr 1 July.
References
Fisher, A.T., Urabe, T., Klaus, A., and the Expedition 301 Scientists, 2005a. Proc. IODP, 301: College Station TX (Integrated Ocean Drilling Program Management International, Inc.). doi:10.2204/iodp.proc.301.2005
Fisher, A.T., Wheat, C.G., Becker, K., Davis, E.E., Jannasch, H., Schroeder, D., Dixon, R., Pettigrew, T.L., Meldrum, R., McDonald, R., Nielsen, M., Fisk, M., Cowen, J., Bach, W., and Edwards, K., 2005b. Scientific and technical design and deployment of long-term, subseafloor observatories for hydrogeologic and related experiments, IODP Expedition 301, eastern flank of Juan de Fuca Ridge. In Fisher, A.T., Urabe, T., Klaus, A., and the Expedition 301 Scientists, Proc. IODP, 301: College Station TX (Integrated Ocean Drilling Program Management International, Inc.).
doi:10.2204/iodp.proc.301.103.2005
|